Emergency Generator - Fuel Capacity

What is the minimum required on-site fuel supply necessary?

Any examples are for illustrative purposes only. 

There are several factors to consider when determining how much fuel a facility should have stored on site for running a generator.  

If the generator serves as a component of an Essential Electrical System (EES) as required for critical care rooms and general care rooms by NFPA 99 (2012 edition) Health Care Facilities Code, Chapter 6, then the licensing authority (typically the state health department) should be consulted for applicable requirements.

“Basic Care” patient rooms in facilities, such as those used for inpatient behavioral health, do not require an EES.  However, in many of these facilities, the generator is the alternate source of power for the illumination of the means of egress, emergency (task) lighting, exit lights, and/or the fire alarm system. NFPA 101 Life Safety Code requires these all to have a minimum duration of 1-1/2 hours (Class 1.5) (which may also be from a battery source).

The Joint Commission Emergency Management Standard EM.02.02.09 EP 5 requires that hospitals identify an alternative means for providing "fuel required for building operations, generators, and essential transport services that the hospital would typically provide."  The facility should assess how it would be affected if outside emergency support could not be obtained for 96 hours.  This does not mean that they need to have 96 hours worth of fuel on site.  The plan could include memoranda of understanding (MOUs) with suppliers to replenish fuel as needed during the emergency period.  Additionally, the plan could be to operate without normal branch of power to reduce fuel consumption, to extend run-time of the available fuel. If the generator is used as the backup power source for the life safety branch of the electrical system, the facility should have enough fuel to run the generator for a least 1-1/2 hours for as long as the building is occupied.
Last updated on March 19, 2021
Manual: Hospital and Hospital Clinics
Chapter: Environment of Care EC

If no, please comment on how we could improve this response.

If you have additional standards-related questions regarding this topic, please use the Standards Online Submission Form
Surgeons in an operating room

Additional Resources

Train your staff with a tool to quickly and efficiently assess standards compliance with our 2021 Hospital Compliance Assessment Workbook.

A group of medical professionals have a discussion in a meeting room

Hospital Webinars

Keep learning with our Hospital Breakfast Briefings Webinar Series. Get a deep dive into our standards, chapter-by-chapter, individually or as a team.

Female doctor using digital tablet in her office.

Looking for Standards?

Get key information your hospital needs to achieve and maintain continuous standards compliance and experience operational improvement.